Demolition of the building C

Demolition of the building C

From 11 March 2019 after more than a month’s break caused by waiting for a demolition permit the works on building C are continuing. The building company took apart the roof from 11 to 15 March and on 18 March continued with the demolition of the perimeter wall that had not met the technical requirements.

Share this post